Construction Activity Reporting Schedule
Date: 29th March, 2024
Site Construction Activities
Block C (Philip Ozuah Block)
Update: The first-floor slab formwork was
completed as planned on the work programme. The steel reinforcement placement
was completed in anticipation of casting the floor slab. The
electrical/mechanical services sleeves placement was completed. The consultant
structural engineer gave the floor slab casting approval.
The procurement of cement an important constituent of concrete was
delayed, due to price increases and subsequent scarcity, which poses a
challenge to casting the floor slab as scheduled. The casting of the floor slab
was delayed for upward of four weeks when the alternative source of the
material procurement approval was obtained. The casting of the first-floor slab
was eventually completed upon surmounting the challenge of the cement
procurement. The raising and casting of the columns to support the second-floor
slab has commenced.
The situation with TimeLine: As of
the 26th- 30th of March, the raising and casting of the columns to support the
second-floor slab has commenced.
�� �
Block D (TY Danjuma Block)
Update: The formwork for the ground beam of
the foundation was completed. The steel reinforcement placement was completed.
The electrical and mechanical services sleeves placement was completed. The
consultant structural engineer gave casting approval for the foundation ground
beam construction. The ground beam casting was completed as striking off of the
formwork commenced. The laterite earth filling has also commenced.
The situation with TimeLine: As of
the 26th- 30th of March, the striking off of the formwork commenced and the
laterite earth filling commenced.
Pictures of Work done on site
Block F (Alumni Block)
Update: The formwork has been completed. The
reinforcement placement has been completed for the ground of the foundation.
The electrical and mechanical services work sleeves placement has been done.
The consultant structural engineer has approved the casting of the ground beam.
The casting of the ground beam has been completed, as the striking off of the
formworks commenced. The laterite earth filling and compaction are ongoing.
The situation with TimeLine: As of
the 26th- 30th of March, the striking off of the formworks commenced. The
laterite earth filling and compaction are ongoing
Pictures
of Work done on site
�
�
Signed,
Arc. Dapo Ojo
Project Client Representative
Adapted for publication by
Seun Abimbola
Media Officer
Please contact:
hostelproject@com.ui.edu.ng
provost@com.ui.edu.ng
Send a WhatsApp message to:
Provost: +2348132243158
Deputy Provost: +2348057325888