Hostel Project for Students of the College of Medicine, University of Ibadan (CoMUI)
Spearheaded by the
Ibadan College of Medicine Alumni Association (ICOMAA)
Construction Activity Reporting Schedule
Date: 1st March 2024.
Site Construction Activities
Block C (Philip Ozuah Block)
Update: The steel reinforcement, electrical, and mechanical sleeves placement on the first-floor slab formwork are ongoing. The contractor mentioned that the formwork, steel reinforcements, and M/E sleeves placement for the casting of the first-floor slab has reached completion, The casting of the floor slab will be delayed due to constraints of cement delivery.
The situation with Timeline:
Pictures of Work done on site
Block D (TY Danjuma Block)
Update: The formworks for the foundation ground beam are ongoing. The mechanical sleeves have been placed with steel reinforcements
The situation with Timeline:
As of the 26th of February � 1st of March, the formworks for the foundation ground beam are at 85% completion.
Pictures of Work done on site
Block F (Alumni Block)
Update: The formwork for the foundation ground beam is ongoing, the water treatment plant for the water to be used for construction has been procured by the contractor. The steel reinforcement and the mechanical sleeves has been properly placed in the formwork.
The situation with Timeline:
As of the 26th of February � 1st of March, the formwork for the foundation ground beam has reached 98% completion.
Pictures of Work done on site
Signed,
Arc. Dapo Ojo
Project Client Representative
Adapted for publication by
�Seun Abimbola
Media Officer
Please contact:
hostelproject@com.ui.edu.ng
provost@com.ui.edu.ng
Send a WhatsApp message to:
Provost: +2348132243158
Deputy Provost: +2348057325888