CoMUI/ICOMAA STUDENT HOSTEL PROJECT UPDATES

Week six report


Hostel Project for Students of the College of Medicine, University of Ibadan (CoMUI)
Spearheaded by the

Ibadan College of Medicine Alumni Association (ICOMAA)


Construction Activity Reporting Schedule

Date: 21st February 2024.

Site Construction Activities

Block C (Philip Ozuah Block)

Update: Moulding of sandcrete blocks, electrical, plumbing sleeves and steel reinforcements placement on first-floor slab formwork commenced.

Pictures of Work done on site

Block D (TY Danjuma Block)

Update: The making of the formwork and steel reinforcements for the ground beams of the foundation work is still ongoing.

The situation with TimeLine: As of the 19th- 23rd of February, the making of the formwork and steel reinforcement is ongoing.

 

 Pictures of Work done on site

 

Block F (Alumni Block)

Update: The formwork work boarding and steel reinforcement placement for the foundation work is still ongoing.

Pictures of Work done on site

Signed,
Arc. Dapo Ojo
Project Client Representative

Adapted for publication by
Seun Abimbola
Media Officer

For Inquiries or to make donations

Please contact:

hostelproject@com.ui.edu.ng

provost@com.ui.edu.ng

Send a WhatsApp message to:

Provost: +2348132243158

Deputy Provost: +2348057325888