Site Construction Activities

Block C (Philip Ozuah Block)

Update: The making of the formwork for the floor beams of the third-floor slab and the blockwork for the wall partitions on the ground floor are still ongoing. 

TimeLine: As of the 1st of June - 7th of June, 2024.

Challenges: There has been no significant challenge in the construction works of this block.

 

Pictures of Work done on site

  

 

Block D (TY Danjuma Block)

Update: The formwork for the floor beams of the floor slab is ongoing.

TimeLine: As of the 1st of June - 7th of June, 2024

Challenges: There has been no significant challenge in the construction works of this block.

 

Pictures of Work done on site

     

 

Block E (Block)

Update: The excavation of trenches for the raft beam is ongoing.

The situation with TimeLine: Not reported yet.

Challenges: There has been no significant challenge stated at the time of reporting.

 

 

 

 

Pictures of Work done on site

       

        

 

Block F (Alumni Block)

Update: The casting of the first-floor slab has commenced, whilst casting of the first-floor columns is about to begin

The situation with Timeline: Not reported yet.

Challenges: There has been no significant challenge in the construction works of this block.

 

 

 

 

 

 