Construction Activity Reporting Schedule

Date: 26th March 2024.

Site Construction Activities

Block C (Philip Ozuah Block)

Update: The raising of steel reinforcement and formwork for the columns to support the second-floor slab continues.

The situation with Timeline:

As of the 18th - 26th of March, the raising of steel reinforcement and formwork for the columns has reached 45% completion.

 

Pictures of Work done on site


Block D (TY Danjuma Block)

Update: The casting of the ground beam for the foundation has been completed and the striking off of formworks commenced with the filling of the laterite earth.

The situation with Timeline:

As of the 18th - 26th of March, the casting of the ground beam for the foundation has been completed. 

Pictures of Work done on site

 

Block F (Alumni Block)
Update: The filling and compaction of the laterite earth in the ground beam has commenced.

Pictures of Work done on site

Signed,
Arc. Dapo Ojo
Project Client Representative

Adapted for publication by
Seun Abimbola
Media Officer

For Inquiries or to make donations

Please contact:

hostelproject@com.ui.edu.ng

provost@com.ui.edu.ng

Send a WhatsApp message to:

Provost: +2348132243158

Deputy Provost: +2348057325888