HOSTEL PROJECT FOR STUDENTS OF THE
COLLEGE OF MEDICINE, UNIVERSITY OF IBADAN (CoMUI)
administered by the
IBADAN COLLEGE OF MEDICINE ALUMNI ASSOCIATION (ICOMAA)
Construction Activity
Reporting Schedule: 13th Report
Date: 29th April 2024
Site Construction
Activities
Block C (Philip Ozuah Block)
Update: Second floor slab.
This block's construction is at the
superstructure stage of the second-floor level. The formwork of this slab has
been completed with the placement of the reinforcement nearing 95% completion
and the electrical/mechanical service sleeves placement at 80%. The blockwork
of the room wall partitions commenced on the ground floor and is ongoing.
The casting of the second-floor slab is slated
for the first week in May.
Pictures of Block C
Update: The construction work on this block is at the substructure stage
with the laterite earth filling, steel reinforcement, and electrical
/mechanical services sleeves placement still ongoing.
Pictures of Work done on site
Block F (Alumni Block)
Update: The substructure stage of the construction is nearing completion
with the commencement of the casting of the ground floor oversite concrete
slab. The contractor informed the team present of the sanitary wares procured
and stored on site.
The casting of the oversite concrete slab was
slated for completion by the close of work on Friday 26th April 2024.
Pictures of Work done on site
�
�
Signed,
Arc. Dapo Ojo
Project Client
Representative
Adapted for publication
by
Seun Abimbola
Media Officer
Please contact:
hostelproject@com.ui.edu.ng
provost@com.ui.edu.ng
Send a WhatsApp message to:
Provost: +2348132243158
Deputy Provost: +2348057325888