Site Construction
Activities
BLOCK C (PHILIP OZUAH
BLOCK)
Update: The construction activities on this block
include the raising of second-floor slab beam formworks and the placing of
reinforcements. Placement of the reinforcements into the beam formworks, second-floor
slab formworks, and striking off of the formwork below the first-floor slab are
ongoing. Block wall partition work commenced and is still ongoing.
As of 18th of
April 2024, the raising and casting of the columns to support the second-floor
slab had commenced.
Progress Pictures of Block
C
�
�
�
BLOCK D (TY DANJUMA
BLOCK)
Update: The laterite earth filling is still ongoing.
Concrete blinding of the ground beam and the placement of the reinforcement has
commenced.
As of 18th of
April 2024, laterite earth filling had reached 60% completion, weak concrete
blinding of the ground beam had reached 40%, while the placement of the
reinforcement had reached 30% completion.
Pictures of Block D
�
BLOCK F (ALUMNI BLOCK)
Update: The placement of reinforcements for the
oversight concrete slab is still ongoing. The laterite earth filling and
compaction are ongoing.
As of the 18th
of April 2024, the laterite earth filling and compaction were ongoing. The
placement of reinforcements for the oversite concrete slab had reached 80%
completion.
Pictures of Block E
�
Signed,
Arc. Dapo Ojo
Project Client
Representative
Adapted for publication
by
�Seun Abimbola
Media Officer
Please contact:
hostelproject@com.ui.edu.ng
provost@com.ui.edu.ng
Send a WhatsApp message to:
Provost: +2348132243158
Deputy Provost: +2348057325888