Site Construction Activities

 

Block C (Philip Ozuah Block)

Update: The completion of the casting of the third-floor slab and raising of the reinforced concrete columns is ongoing.

Timeline: As at 12th of August - 23rd of August, the program of work is being followed.

Challenges: There are no significant challenges in the construction works of 

this block.

Pictures of work done on site

    

    

    

 

Block D (TY Danjuma Block)

Update: The formwork for the second-floor slab is ongoing.

TimeLine: As at 12th of August - 23rd of August, the program of work is being followed.

Challenges: There are no significant challenges on the construction works of this block.

 

Pictures of work done on site

    

    

    

 

Block E (Block)

Update: The placement of steel reinforcement and plumbing sleeves for the oversite concrete slab is ongoing.

Timeline: As at 12th of August - 23rd of August, the program of work is being followed.

Challenges: There are no significant challenges in the construction works of this block.

Pictures of work done on site

    

    

 

 

Block F (Alumni Block)

Update: The hacking-off of the formwork on the slab soffit, the raising of the formwork and reinforcements for the columns and the slabs are ongoing.

Timeline: As at 12th of August - 23rd of August, the program of work is being followed.

Challenges: There are no significant challenges in the construction works of this block.

Pictures of work done onsite

 

    

    

         

 

       

Signed,

Arc. Dapo Ojo