Hostel Project for Students of the College of Medicine, University of Ibadan (CoMUI) Administered by the
Ibadan College of Medicine Alumni Association (ICOMAA)
Construction Activity Reporting Schedule: 29th Report
Date: 4th September 2024.
Site Construction Activities
Block C (Philip Ozuah Block)
Update: The completion of the casting of the third-floor slab and raising of the reinforced concrete columns
Timeline: As at 26th of August - 30th of August, the program of work is being followed.
Challenges: There are no significant challenges in the construction works of
this block.
Pictures of work done on site
Block D (TY Danjuma Block)
Update: The steel reinforcement, and mechanical/electrical service sleeves placement for the casting of the second-floor slab are ongoing.
Timeline: As of 26th of August - 30th of August, the steel reinforcement, and mechanical/electrical service sleeves placement for the casting of the second-floor slab are nearing completion.
Challenges: There are no significant challenges in the construction works of this block.
Pictures of Work done on site
Block E (Block)
Update: The oversite concrete casting, steel reinforcement, and mechanical /electrical services placement are ongoing.
TimeLine: As at 26th of August - 30th of August, the oversite concrete casting, steel reinforcement, and mechanical/electrical services placement are nearing 50% completion.
Challenges: There are no significant challenges in the construction works of this block to report.
Pictures of work done onsite
Block F (Alumni Block)
Update: The striking-off of the formwork on the first-floor slab soffit, propping of the formwork and placement of the steel reinforcement for the third-floor slab.
Timeline: As at 26th of August - 30th of August, the program of work is being followed.
Challenges: There are no significant challenges in the construction works of this block.
Pictures of work done onsite
Signed,
Arc. Dapo Ojo
Project Client Representative
Adapted for publication by
‘Seun Abimbola
Media Officer